If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in:

Course Name: Quantitative Aptitude

  • 1] 5 days
  • 2] 40 days
  • 3] 10 days
  • 4] 20 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
2
Discuss

If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster then C, than the number of days C alone can complete the work is ?

  • 1] 44 days
  • 2] 33 days
  • 3] 22 days
  • 4] 11 days
Solution
3
Discuss

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • 1] 28 days
  • 2] 36 days
  • 3] 48 days
  • 4] 52 days
Solution
4
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
5
Discuss

A, B and C completed a work costing Rs. 1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A ?

  • 1] Rs. 600
  • 2] Rs. 750
  • 3] Rs. 800
  • 4] Rs. 900
Solution
6
Discuss

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?

  • 1] 12 days
  • 2] 14 days
  • 3] 36 days
  • 4] 40 days
Solution
7
Discuss

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

  • 4]

    \({ \text{7}}\frac{3}{4}{ \text{ days}}\)

Solution
8
Discuss

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?

  • 1] 30 days
  • 2] 27 days
  • 3] 20 days
  • 4] 25 days
Solution
9
Discuss

Anuj and Manoj can together paint their house in 30 days. After working for 20 days, Anuj has to go out and Manoj finished the remaining working the next 30 days. If Manoj had gone away after 20 days instead of Anuj, then Anuj would have completed the remaining work in ?

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 35 days
Solution
10
Discuss

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?

  • 1] 5 days
  • 2] 6 days
  • 3] 10 days
  • 4] 12 days
Solution