Quiz Discussion

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

Course Name: Quantitative Aptitude

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can do a piece of work in 30 days, B and C together can do it in 20 days, A starts the work and works on it for 5 days, B takes up and work for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work where doing it separately is = ?

  • 1] 120 days
  • 2] 40 days
  • 3] 60 days
  • 4] 24 days
Solution
2
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
3
Discuss

A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:

  • 1] 9 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
4
Discuss

P is thrice as good a workman as Q and together they finish a piece of work in 24 days. The number of days taken by P alone to finish the work is:

  • 1]

    25 days

  • 2]

    22 days

  • 3]

    32 days

  • 4]

    34 days

Solution
5
Discuss

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 7 days
Solution
6
Discuss

Three taps A, B and C together can fill an empty cistern in 10 minutes. The tap A alone can fill it in 30 minutes and the tap B alone in 40 minutes. How long will the tap C alone take to fill it?

  • 1] 16 minutes
  • 2] 24 minutes
  • 3] 32 minutes
  • 4] 40 minutes
Solution
7
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution
8
Discuss

A can do a piece of work in 4 hours, B and C together in 3 hours, and A and C together in 2 hours. How long will B alone take to do it ?

  • 1] 8 hours
  • 2] 10 hours
  • 3] 12 hours
  • 4] 24 hours
Solution
9
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
10
Discuss

A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were

  • 1]

    12

  • 2]

    15

  • 3]

    18

  • 4]

    24

Solution
# Quiz