If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

Course Name: Quantitative Aptitude

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?

  • 1] 240
  • 2] 140
  • 3] 280
  • 4] 150
  • 5] None of these
Solution
2
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
3
Discuss

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?

  • 1] 24
  • 2] 20
  • 3] 16
  • 4] 18
Solution
4
Discuss

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

  • 1] 12 days
  • 2] 15 days
  • 3] 16 days
  • 4] 18 days
Solution
5
Discuss

Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:

  • 1] 39 min.
  • 2] 46 min
  • 3] 40 min.
  • 4] 45 min.
Solution
6
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    22 1/2 day

  • 3]

    25 days

  • 4]

    30 days

Solution
7
Discuss

Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?

  • 1] Rs. 600, Rs. 550, Rs. 250
  • 2] Rs. 600, Rs. 525, Rs. 275
  • 3] Rs. 600, Rs. 500, Rs. 300
  • 4] Rs. 500, Rs. 525, Rs. 375
Solution
8
Discuss

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?

  • 1] 5 days
  • 2] 6 days
  • 3] 10 days
  • 4] 12 days
Solution
9
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
10
Discuss

P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution
# Quiz