Quiz Discussion

A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?

 

Course Name: Quantitative Aptitude

  • 1]

    \(10\frac{1}{2}{ \text{days}}\)

  • 2]

    \(12\frac{2}{3}{ \text{days}}\)

  • 3]

    \(13\frac{1}{3}{ \text{days}}\)

  • 4]

    \(8\frac{1}{4}{ \text{days}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.

  • 1] 25 days
  • 2] 30 days
  • 3] 60 days
  • 4] 65 days
Solution
2
Discuss

40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?

  • 1]

    \({ \text{7}}\frac{2}{3}{ \text{ days}}\)

  • 2]

    \({ \text{6}}\frac{1}{5}{ \text{ days}}\)

  • 3]

    \({ \text{8}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

Solution
3
Discuss

A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?

  • 1] 91 days
  • 2] 100 days
  • 3] 175 days
  • 4] None of these
Solution
4
Discuss

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?

  • 1] 12 days
  • 2] 14 days
  • 3] 36 days
  • 4] 40 days
Solution
5
Discuss

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

  • 1] 24 days
  • 2] 32 days
  • 3] 40 days
  • 4] 48 days
Solution
6
Discuss

Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • 1] 14
  • 2] 17
  • 3] 12
  • 4] 15
Solution
7
Discuss

A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
8
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
9
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
10
Discuss

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

  • 1] 5 days
  • 2] 6 days
  • 3] 9 days
  • 4] 10 days
Solution
# Quiz