A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?
\(10\frac{1}{2}{ \text{days}}\)
\(12\frac{2}{3}{ \text{days}}\)
\(13\frac{1}{3}{ \text{days}}\)
\(8\frac{1}{4}{ \text{days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
Solution |
2
Discuss
|
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
Solution |
3
Discuss
|
A and B together can do a job in 2 days; B and C can do it in 4 days; A and C in \({ \text{2}}\frac{2}{5}\) days. The number of days required for A to do the job alone is = ?
Solution |
4
Discuss
|
A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:
Solution |
5
Discuss
|
If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :
Solution |
6
Discuss
|
A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?
Solution |
7
Discuss
|
A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?
Solution |
8
Discuss
|
A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?
Solution |
9
Discuss
|
Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?
Solution |
10
Discuss
|
A and B together can do a piece of work in 30 days, B and C together can do it in 20 days, A starts the work and works on it for 5 days, B takes up and work for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work where doing it separately is = ?
Solution |