Quiz Discussion

A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full and if 40, 000 litres of petrol is used daily, the supply fails in 90 days. If 32, 000 litres of petrol used daily, it fails in 60 days. How much petrol can be used daily without the supply ever failing?

Course Name: Quantitative Aptitude

  • 1] 64000 litres
  • 2] 56000 litres
  • 3] 60000 litres
  • 4] 78000 litres
  • 5] None of these
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60

Solution
2
Discuss

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

  • 1] 30 days
  • 2] 35 days
  • 3] 40 days
  • 4] 45 days
Solution
3
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
4
Discuss

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
5
Discuss

A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?

 

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 30 days
Solution
6
Discuss

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
7
Discuss

P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?

 

  • 1] 10 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
8
Discuss

A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:

  • 1] 15 days
  • 2] 16 days
  • 3] 18 days
  • 4] 20 days
Solution
9
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
10
Discuss

A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?

  • 1] 20 days
  • 2] 24 days
  • 3] 36 days
  • 4] 72 days
Solution
# Quiz