A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Course Name: Quantitative Aptitude

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • 1] 14
  • 2] 17
  • 3] 12
  • 4] 15
Solution
2
Discuss

Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?

  • 1] 3 : 2
  • 2] 2 : 3
  • 3] 3 : 4
  • 4] 4 : 3
Solution
3
Discuss

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?

  • 1] 12 days
  • 2] 14 days
  • 3] 36 days
  • 4] 40 days
Solution
4
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
5
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
6
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
7
Discuss

An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
8
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
9
Discuss

A can do a piece of work in 70 days and B is 40% more efficient then A. Then the number of days taken by B to do the same work is = ?

  • 1] 40 dayd
  • 2] 60 days
  • 3] 50 days
  • 4] 45 days
Solution
10
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution