A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?
Solution |
2
Discuss
|
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Solution |
3
Discuss
|
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?
Solution |
4
Discuss
|
A group of workers was put on a job. From second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?
Solution |
5
Discuss
|
A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?
Solution |
6
Discuss
|
If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?
Solution |
7
Discuss
|
12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?
Solution |
8
Discuss
|
A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?
Solution |
9
Discuss
|
A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Solution |
10
Discuss
|
Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?
Solution |