A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

Course Name: Quantitative Aptitude

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

There is provision of food in fort for 1200 soldiers for 60 days. After 15 days, 200 soldiers leave the fort. Remaining food will last for how many days?

  • 1] 56 days
  • 2] 50 days
  • 3] 54 days
  • 4] 48 days
Solution
2
Discuss

A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?

  • 1] 8 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
3
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution
4
Discuss

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution
5
Discuss

X can copy 80 pages in 20 hours, x and y together can copy 135 pages in 27 hours. Then y can copy 20 pages in ?

  • 1] 20 hours
  • 2] 24 hours
  • 3] 3 hours
  • 4] 12 hours
Solution
6
Discuss

A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?

  • 1] 2 days
  • 2] 3 days
  • 3] 5 days
  • 4] 10 days
Solution
7
Discuss

If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 40 days
Solution
8
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
9
Discuss

4 men and 10 women were put on work. They completed \(\frac{1}{3}\) of the work in 4 days. After this 2 men and 2 women were increased. They completed \(\frac{2}{9}\) more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased?

 

  • 1] 8
  • 2] 32
  • 3] 50
  • 4] 55
Solution
10
Discuss

18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?

  • 1] 54 days
  • 2] 63 days
  • 3] 76 days
  • 4] 81 days
  • 5] None of these
Solution