Quiz Discussion

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

Course Name: Quantitative Aptitude

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
2
Discuss

If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?

  • 1] 6 days
  • 2] 7 days
  • 3] 8 days
  • 4] 10 days
Solution
3
Discuss

Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?

  • 1] Rs. 600, Rs. 550, Rs. 250
  • 2] Rs. 600, Rs. 525, Rs. 275
  • 3] Rs. 600, Rs. 500, Rs. 300
  • 4] Rs. 500, Rs. 525, Rs. 375
Solution
4
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution
5
Discuss

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
6
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
7
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
8
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
9
Discuss

A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?

  • 1] 24 days
  • 2] 32 days
  • 3] 40 days
  • 4] 48 days
Solution
10
Discuss

Two pipes, P and Q can fill a cistern in 12 and 15 minutes respectively. Both are opened together, but at the end of 3 minutes, P is turned off. In how many more minutes will Q fill the cistern?

  • 1]

    7 minutes

  • 2]

    \(7\frac{1}{2}\) minutes

  • 3]

    8 minutes

  • 4]

    \(8\frac{1}{4}\) minutes

Solution
# Quiz