There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage ant it was completely used for eating purpose?

Course Name: Quantitative Aptitude

  • 1] 80 days
  • 2] 72 days
  • 3] 100 days
  • 4] 120 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?

  • 1] 10
  • 2] 15
  • 3] 18
  • 4] 20
Solution
2
Discuss

Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?

  • 1]

    4

  • 2]

    5

  • 3]

    3

  • 4]

    \({ \text{2}}\frac{2}{5}\)

Solution
3
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
4
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
5
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
6
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
7
Discuss

Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:

  • 1] 39 min.
  • 2] 46 min
  • 3] 40 min.
  • 4] 45 min.
Solution
8
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
9
Discuss

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?

  • 1] A Rs. 24, B Rs. 54, C Rs. 162
  • 2] A Rs. 22, B Rs.50, C Rs. 132
  • 3] A Rs. 26, B Rs. 52, C Rs. 142
  • 4] A Rs. 20, B Rs. 44, C Rs. 182
Solution
10
Discuss

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
# Quiz