Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?
Solution |
2
Discuss
|
X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
Solution |
3
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
4
Discuss
|
4 men and 10 women were put on work. They completed \(\frac{1}{3}\) of the work in 4 days. After this 2 men and 2 women were increased. They completed \(\frac{2}{9}\) more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased?
Solution |
5
Discuss
|
A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:
Solution |
6
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |
7
Discuss
|
A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?
Solution |
8
Discuss
|
A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days. A and C together can complete the same task in 40 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone?
Solution |
9
Discuss
|
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Solution |
10
Discuss
|
A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?
Solution |