Quiz Discussion

A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?

Course Name: Quantitative Aptitude

  • 1] 8 days
  • 2] 9 days
  • 3] 10 days
  • 4] 11 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it?

  • 1] 10 days
  • 2] 11 days
  • 3] 9 days
  • 4] 12 days
Solution
2
Discuss

42 women can do a piece of work in 18 days, How many women would be required do the same work in 21 days.

  • 1] 35
  • 2] 36
  • 3] 37
  • 4] 38
Solution
3
Discuss

16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?

  • 1] 21
  • 2] 28
  • 3] 16
  • 4] 14
Solution
4
Discuss

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

  • 1] 12 days
  • 2] 15 days
  • 3] 16 days
  • 4] 18 days
Solution
5
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
6
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
7
Discuss

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

  • 1] 75
  • 2] 100
  • 3] 125
  • 4] 50
Solution
8
Discuss

A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?

 

  • 1]

    \(10\frac{1}{2}{ \text{days}}\)

  • 2]

    \(12\frac{2}{3}{ \text{days}}\)

  • 3]

    \(13\frac{1}{3}{ \text{days}}\)

  • 4]

    \(8\frac{1}{4}{ \text{days}}\)

Solution
9
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
10
Discuss

12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?

  • 1]

    \({ \text{20}}\frac{4}{7}{ \text{ days}}\)

  • 2]

    \({ \text{2}}\frac{4}{7}{ \text{ days}}\)

  • 3]

    \({ \text{20}}\frac{3}{7}{ \text{ days}}\)

  • 4]

    18 days

Solution
# Quiz