Quiz Discussion

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?

Course Name: Quantitative Aptitude

  • 1] 8 days
  • 2] 6 days
  • 3] 8 days
  • 4] 12 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage ant it was completely used for eating purpose?

  • 1] 80 days
  • 2] 72 days
  • 3] 100 days
  • 4] 120 days
Solution
2
Discuss

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
3
Discuss

Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
4
Discuss

A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days. How many days will B take to complete the task if he works alone?

  • 1]

    9 days

  • 2]

    7 days

  • 3]

    5 days

  • 4]

    3 days

  • 5]

    None of these

Solution
5
Discuss

A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution
6
Discuss

A and B together can do a job in 2 days; B and C can do it in 4 days; A and C in \({ \text{2}}\frac{2}{5}\) days. The number of days required for A to do the job alone is = ?

 

  • 1] 1
  • 2] 3
  • 3] 6
  • 4] 12
Solution
7
Discuss

A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
8
Discuss

Anuj and Manoj can together paint their house in 30 days. After working for 20 days, Anuj has to go out and Manoj finished the remaining working the next 30 days. If Manoj had gone away after 20 days instead of Anuj, then Anuj would have completed the remaining work in ?

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 35 days
Solution
9
Discuss

Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?

  • 1] 20 minutes
  • 2] 30 minutes
  • 3] 40 minutes
  • 4] 50 minutes
Solution
10
Discuss

A tank can be filled with water by two pipes A and B together in 36 minutes. If the pipe B was stopped after 30 minutes, the tank is filled in 40 minutes. The pipe B can alone fill the tank in:

  • 1] 45 minutes
  • 2] 60 minutes
  • 3] 75 minutes
  • 4] 90 minutes
Solution
# Quiz