A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

Course Name: Quantitative Aptitude

  • 1]

    5 days

  • 2]

    6 days

  • 3]

    10 days

  • 4]

    10* 1/2 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job ?

  • 1] 27 days
  • 2] 36 days
  • 3] 40 days
  • 4] 54 days
Solution
2
Discuss

A man is twice as fast as a women and a woman is twice as fast as a boy in doing a work. If all of them, a man , a woman and a boy can finish the work in 7 days, a boy will do it alone ?

  • 1] 49 days
  • 2] 7 days
  • 3] 6 days
  • 4] 42 days
Solution
3
Discuss

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

  • 1] 3 days
  • 2] 4 days
  • 3] 4.5 days
  • 4] 5.4 days
Solution
4
Discuss

Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • 1] 14
  • 2] 17
  • 3] 12
  • 4] 15
Solution
5
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
6
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
7
Discuss

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?

  • 1] A Rs. 24, B Rs. 54, C Rs. 162
  • 2] A Rs. 22, B Rs.50, C Rs. 132
  • 3] A Rs. 26, B Rs. 52, C Rs. 142
  • 4] A Rs. 20, B Rs. 44, C Rs. 182
Solution
8
Discuss

40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?

  • 1]

    \({ \text{7}}\frac{2}{3}{ \text{ days}}\)

  • 2]

    \({ \text{6}}\frac{1}{5}{ \text{ days}}\)

  • 3]

    \({ \text{8}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

Solution
9
Discuss

A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?

  • 1]

    \(\frac{{80}}{{13}}{ \text{days}}\)

  • 2]

    \(\frac{{70}}{{13}}{ \text{days}}\)

  • 3]

    \(\frac{{75}}{{13}}{ \text{days}}\)

  • 4]

    \(\frac{{60}}{{13}}{ \text{days}}\)

Solution
10
Discuss

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

  • 1]

    \(9\frac{1}{5}\) days

  • 2]

    \(9\frac{2}{7}\) days

  • 3]

    \(9\frac{3}{5}\) days

  • 4]

    10

Solution