A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

Course Name: Quantitative Aptitude

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
2
Discuss

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • 1] 28 days
  • 2] 36 days
  • 3] 48 days
  • 4] 52 days
Solution
3
Discuss

Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.

  • 1] 3150
  • 2] 3450
  • 3] 3500
  • 4] 3600
  • 5] None of these
Solution
4
Discuss

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

  • 1]

    \(13\frac{1}{3}{ \text{days}}\)

  • 2]

    14 days

  • 3]

    15 days

  • 4]

    \(16\frac{2}{3}{ \text{days}}\)

Solution
5
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
6
Discuss

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?

  • 1] A Rs. 24, B Rs. 54, C Rs. 162
  • 2] A Rs. 22, B Rs.50, C Rs. 132
  • 3] A Rs. 26, B Rs. 52, C Rs. 142
  • 4] A Rs. 20, B Rs. 44, C Rs. 182
Solution
7
Discuss

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
8
Discuss

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?

 

  • 1] 45
  • 2] 40
  • 3] 35
  • 4] 30
Solution
9
Discuss

A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?

  • 1] 91 days
  • 2] 100 days
  • 3] 175 days
  • 4] None of these
Solution
10
Discuss

A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?

  • 1] 8 days
  • 2] 9 days
  • 3] 10 days
  • 4] 11 days