A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution |
2
Discuss
|
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work ?
Solution |
3
Discuss
|
Raj can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijit joined and completed it working for 10 days. In how many days Raj and Abhijit can do the complete work, working together?
Solution |
4
Discuss
|
If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?
Solution |
5
Discuss
|
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
Solution |
6
Discuss
|
If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?
Solution |
7
Discuss
|
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Solution |
8
Discuss
|
Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?
Solution |
9
Discuss
|
A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for
Solution |
10
Discuss
|
A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?
Solution |