Quiz Discussion

A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?

Course Name: Quantitative Aptitude

  • 1] 10 days
  • 2] 20 days
  • 3] 25 days
  • 4] 15 days
  • 5] 24 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?

  • 1] 18 days
  • 2] 24 days
  • 3] 9 days
  • 4] 12 days
Solution
2
Discuss

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

  • 1] 5 days
  • 2] 6 days
  • 3] 9 days
  • 4] 10 days
Solution
3
Discuss

A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution
4
Discuss

Anuj and Manoj can together paint their house in 30 days. After working for 20 days, Anuj has to go out and Manoj finished the remaining working the next 30 days. If Manoj had gone away after 20 days instead of Anuj, then Anuj would have completed the remaining work in ?

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 35 days
Solution
5
Discuss

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?

  • 1] 30 days
  • 2] 27 days
  • 3] 20 days
  • 4] 25 days
Solution
6
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
7
Discuss

If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
8
Discuss

Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?

  • 1] 15
  • 2] 25
  • 3] 18
  • 4] 16
Solution
9
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
10
Discuss

There is provision of food in fort for 1200 soldiers for 60 days. After 15 days, 200 soldiers leave the fort. Remaining food will last for how many days?

  • 1] 56 days
  • 2] 50 days
  • 3] 54 days
  • 4] 48 days
Solution
# Quiz