If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?
Solution |
2
Discuss
|
A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?
Solution |
3
Discuss
|
A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full and if 40, 000 litres of petrol is used daily, the supply fails in 90 days. If 32, 000 litres of petrol used daily, it fails in 60 days. How much petrol can be used daily without the supply ever failing?
Solution |
4
Discuss
|
Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:
Solution |
5
Discuss
|
Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?
Solution |
6
Discuss
|
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Solution |
7
Discuss
|
If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?
Solution |
8
Discuss
|
If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?
Solution |
9
Discuss
|
To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Solution |
10
Discuss
|
Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?
Solution |