A can do in one day three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is =?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?
Solution |
2
Discuss
|
A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?
Solution |
3
Discuss
|
While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?
Solution |
4
Discuss
|
A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?
Solution |
5
Discuss
|
A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Solution |
6
Discuss
|
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Solution |
7
Discuss
|
If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in = ?
Solution |
8
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |
9
Discuss
|
A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:
Solution |
10
Discuss
|
If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?
Solution |