A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

Course Name: Quantitative Aptitude

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?

  • 1] 5 days
  • 2] 6 days
  • 3] 7 days
  • 4] 8 days
Solution
2
Discuss

A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?

  • 1] Rs. 150
  • 2] Rs. 225
  • 3] Rs. 250
  • 4] Rs. 300
Solution
3
Discuss

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

  • 1] 10 days
  • 2] 9 days
  • 3] 12 days
  • 4] 15 days
Solution
4
Discuss

A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?

  • 1] 16 days
  • 2] 24 days
  • 3] 35 days
  • 4] 28 days
Solution
5
Discuss

Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?

  • 1] 1 hour
  • 2] 2 hours
  • 3] 3 hours
  • 4] 4 hours
  • 5] 5 hours
Solution
6
Discuss

The charges per hour of internet surfing is increased by 25% then find the percentage decrease in the time period of surfing user (a net savy) who can afford only 10% increase in expenditure:

  • 1] 22%
  • 2] 12%
  • 3] 15%
  • 4] 9.09%
Solution
7
Discuss

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?

  • 1] 100
  • 2] 60
  • 3] 75
  • 4] None of these
Solution
8
Discuss

While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 1] 3 days
  • 2] 4 days
  • 3] 2.1 days
  • 4] 3.6 days
Solution
9
Discuss

A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?

 

  • 1]

    \(9\frac{1}{3}{ \text{days}}\)

  • 2]

    11 days

  • 3]

    \(12\frac{1}{4}{ \text{days}}\)

  • 4]

    \(16\frac{1}{3}{ \text{days}}\)

Solution
10
Discuss

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?

  • 1] 20 days
  • 2] 21 days
  • 3] 22 days
  • 4] 24 days
Solution
# Quiz