The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

Course Name: Quantitative Aptitude

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60

Solution
2
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
3
Discuss

A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?

  • 1] 5
  • 2] 6
  • 3] 9
  • 4] 13
Solution
4
Discuss

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

  • 1] 60
  • 2] 45
  • 3] 40
  • 4] 30
Solution
5
Discuss

A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?

 

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 30 days
Solution
6
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
7
Discuss

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
8
Discuss

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 7 days
Solution
9
Discuss

A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?

  • 1]

    \({ \text{3}}\frac{5}{{12}}\)

  • 2]

    \({ \text{3}}\frac{9}{{13}}\)

  • 3]

    \({ \text{7}}\frac{5}{{12}}\)

  • 4]

    \({ \text{7}}\frac{5}{{13}}\)

Solution
10
Discuss

A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?

 

  • 1]

    \(9\frac{1}{3}{ \text{days}}\)

  • 2]

    11 days

  • 3]

    \(12\frac{1}{4}{ \text{days}}\)

  • 4]

    \(16\frac{1}{3}{ \text{days}}\)

Solution