A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution |
2
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be
Solution |
3
Discuss
|
16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work ?
Solution |
4
Discuss
|
A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were
Solution |
5
Discuss
|
There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage ant it was completely used for eating purpose?
Solution |
6
Discuss
|
A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?
Solution |
7
Discuss
|
Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?
Solution |
8
Discuss
|
Find in what ratio will the total wages of the workers of a factory be increased or decreased if there is a reduction in the number of workers in the ratio 13 : 10 and an increment in their wages in the ratio 15: 26.
Solution |
9
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
Solution |
10
Discuss
|
A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days. A and C together can complete the same task in 40 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone?
Solution |