Three pipes A,B and C attached to a cistern. A can fill it in 10 min, B in 15 min, C is a waste pipe for emptying it. After opening both the pipes A and B, a man leaves the cistern and returns when the cistern should have been just full. Finding, however, that the waste pipe had left open, he closes it and the cistern now gets filled in 2 min. In how much time the pipe C, if opened alone, empty the full cistern?

Course Name: Quantitative Aptitude

  • 1] 12 min
  • 2] 16 min
  • 3] 18 min
  • 4] 15 min
  • 5] None of these
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
2
Discuss

4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?

  • 1] 4
  • 2] 8
  • 3] 12
  • 4] 16
Solution
3
Discuss

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 7 days
Solution
4
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
5
Discuss

If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?

  • 1] 35 days
  • 2] 50 days
  • 3] 45 days
  • 4] 40 days
Solution
6
Discuss

A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?

  • 1] 30 days
  • 2] 40 days
  • 3] 50 days
  • 4] 70 days
Solution
7
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
8
Discuss

At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?

  • 1] IITian is 20% less efficient
  • 2] NITian is 33.33% less efficien
  • 3] NIT is 25% less efficient
  • 4] IIT is 33.33% less efficient
  • 5] Cannot be determined
Solution
9
Discuss

16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?

  • 1] 21
  • 2] 28
  • 3] 16
  • 4] 14
Solution
10
Discuss

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

  • 1]

    5 days

  • 2]

    6 days

  • 3]

    10 days

  • 4]

    10* 1/2 days

Solution