4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?

Course Name: Quantitative Aptitude

  • 1] 4
  • 2] 8
  • 3] 12
  • 4] 16
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
2
Discuss

A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?

  • 1] 20 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
3
Discuss

A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?

  • 1] 2 days
  • 2] 3 days
  • 3] 5 days
  • 4] 10 days
Solution
4
Discuss

A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?

 

  • 1] 5 hours
  • 2] 4 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
5
Discuss

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

  • 1] 10 days
  • 2] 9 days
  • 3] 12 days
  • 4] 15 days
Solution
6
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
7
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
8
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
9
Discuss

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
10
Discuss

A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?

  • 1] 240
  • 2] 140
  • 3] 280
  • 4] 150
  • 5] None of these
Solution
# Quiz