A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?
\(\frac{7}{{24}}{ \text{days}}\)
\({ \text{3}}\frac{3}{7}{ \text{days}}\)
4 days
\({ \text{3}}\frac{1}{{13}}{ \text{days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Solution |
2
Discuss
|
A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?
Solution |
3
Discuss
|
A and B together can do a job in 2 days; B and C can do it in 4 days; A and C in \({ \text{2}}\frac{2}{5}\) days. The number of days required for A to do the job alone is = ?
Solution |
4
Discuss
|
A pipe can fill a tank in 0.9 hours and another pipe can empty in 0.7 hours. If tank is completely filled and both pipes are opened simultaneously then 450 liters of water is removed from the tank is 2.5 hours. What is the capacity of the tank?
Solution |
5
Discuss
|
A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?
Solution |
6
Discuss
|
A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?
Solution |
7
Discuss
|
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in ?
Solution |
8
Discuss
|
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Solution |
9
Discuss
|
A and B together can do a piece of work in 30 days, B and C together can do it in 20 days, A starts the work and works on it for 5 days, B takes up and work for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work where doing it separately is = ?
Solution |
10
Discuss
|
X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?
Solution |