A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?
Solution |
2
Discuss
|
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Solution |
3
Discuss
|
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
Solution |
4
Discuss
|
If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?
Solution |
5
Discuss
|
42 women can do a piece of work in 18 days, How many women would be required do the same work in 21 days.
Solution |
6
Discuss
|
Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:
Solution |
7
Discuss
|
A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?
Solution |
8
Discuss
|
12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?
Solution |
9
Discuss
|
A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?
Solution |
10
Discuss
|
Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?
Solution |