Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?
Solution |
2
Discuss
|
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Solution |
3
Discuss
|
A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:
Solution |
4
Discuss
|
A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?
Solution |
5
Discuss
|
If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:
Solution |
6
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
7
Discuss
|
25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?
Solution |
8
Discuss
|
A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?
Solution |
9
Discuss
|
A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?
Solution |
10
Discuss
|
A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?
Solution |