A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?

Course Name: Quantitative Aptitude

  • 1] 12 days
  • 2] 13 days
  • 3] 14 days
  • 4] 15 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?

  • 1]

    \({ \text{14}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    \({ \text{15}}\frac{2}{3}{ \text{ days}}\)

  • 3]

    \({ \text{16}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{18}}\frac{2}{3}{ \text{ days}}\)

Solution
2
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
3
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
4
Discuss

Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?

  • 1] 3 : 2
  • 2] 2 : 3
  • 3] 3 : 4
  • 4] 4 : 3
Solution
5
Discuss

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

  • 1]

    \(9\frac{1}{5}\) days

  • 2]

    \(9\frac{2}{7}\) days

  • 3]

    \(9\frac{3}{5}\) days

  • 4]

    10

Solution
6
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
7
Discuss

4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?

  • 1] 4
  • 2] 8
  • 3] 12
  • 4] 16
Solution
8
Discuss

X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in ?

  • 1] 27 days
  • 2] 36 days
  • 3] 42 days
  • 4] 18 days
Solution
9
Discuss

While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 1] 3 days
  • 2] 4 days
  • 3] 2.1 days
  • 4] 3.6 days
Solution
10
Discuss

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  • 1]

    8 days

  • 2]

    10 days

  • 3]

    12 days

  • 4]

    15 days

Solution