Quiz Discussion

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

Course Name: Quantitative Aptitude

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two pipes, P and Q can fill a cistern in 12 and 15 minutes respectively. Both are opened together, but at the end of 3 minutes, P is turned off. In how many more minutes will Q fill the cistern?

  • 1]

    7 minutes

  • 2]

    \(7\frac{1}{2}\) minutes

  • 3]

    8 minutes

  • 4]

    \(8\frac{1}{4}\) minutes

Solution
2
Discuss

If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:

  • 1] 48 days
  • 2] 36 days
  • 3] 45 days
  • 4] 50 days
Solution
3
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
4
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
5
Discuss

A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?

  • 1] 12 days
  • 2] 13 days
  • 3] 14 days
  • 4] 15 days
Solution
6
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
7
Discuss

A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?

  • 1] 16 days
  • 2] 24 days
  • 3] 35 days
  • 4] 28 days
Solution
8
Discuss

There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?

  • 1] 15
  • 2] 30
  • 3] 25
  • 4] 10
  • 5] None of these
Solution
9
Discuss

A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?

  • 1]

    \(\frac{{80}}{{13}}{ \text{days}}\)

  • 2]

    \(\frac{{70}}{{13}}{ \text{days}}\)

  • 3]

    \(\frac{{75}}{{13}}{ \text{days}}\)

  • 4]

    \(\frac{{60}}{{13}}{ \text{days}}\)

Solution
10
Discuss

Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:

  • 1]

    \(\frac{2}{3}\) hours

  • 2]

    \(\frac{3}{4}\) hours

  • 3]

    \(\frac{3}{2}\) hours

  • 4]

    \(\frac{4}{3}\) hours

Solution
# Quiz