A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:
8 days
10 days
12 days
15 days
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?
Solution |
2
Discuss
|
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?
Solution |
3
Discuss
|
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
Solution |
4
Discuss
|
A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:
Solution |
5
Discuss
|
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
Solution |
6
Discuss
|
P is thrice as good a workman as Q and together they finish a piece of work in 24 days. The number of days taken by P alone to finish the work is:
Solution |
7
Discuss
|
A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?
Solution |
8
Discuss
|
Find in what ratio will the total wages of the workers of a factory be increased or decreased if there is a reduction in the number of workers in the ratio 13 : 10 and an increment in their wages in the ratio 15: 26.
Solution |
9
Discuss
|
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Solution |
10
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
Solution |