A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

Course Name: Quantitative Aptitude

  • 1]

    \({ \text{ 4}}\frac{4}{5}{ \text{ days}}\)

  • 2]

    \({ \text{ 3}}\frac{1}{3}{ \text{ days}}\)

  • 3]

    \({ \text{ 5}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{2}}\frac{2}{3}{ \text{ days}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?

  • 1] 21
  • 2] 28
  • 3] 16
  • 4] 14
Solution
2
Discuss

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

  • 4]

    \({ \text{7}}\frac{3}{4}{ \text{ days}}\)

Solution
3
Discuss

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

  • 1]

    \(13\frac{1}{3}{ \text{days}}\)

  • 2]

    14 days

  • 3]

    15 days

  • 4]

    \(16\frac{2}{3}{ \text{days}}\)

Solution
4
Discuss

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?

  • 1] 20 days
  • 2] 21 days
  • 3] 22 days
  • 4] 24 days
Solution
5
Discuss

A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?

  • 1] 3 days
  • 2] 5 days
  • 3] 4 days
  • 4] 2 days
Solution
6
Discuss

While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 1] 3 days
  • 2] 4 days
  • 3] 2.1 days
  • 4] 3.6 days
Solution
7
Discuss

An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
8
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
9
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
10
Discuss

16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work ?

  • 1] 6
  • 2] 12
  • 3] 16
  • 4] None of these
Solution
# Quiz