A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

Course Name: Quantitative Aptitude

  • 1]

    81

  • 2]

    82

  • 3]

    83

  • 4]

    84

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
2
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution
3
Discuss

A man is twice as fast as a women and a woman is twice as fast as a boy in doing a work. If all of them, a man , a woman and a boy can finish the work in 7 days, a boy will do it alone ?

  • 1] 49 days
  • 2] 7 days
  • 3] 6 days
  • 4] 42 days
Solution
4
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
5
Discuss

A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job ?

  • 1] 27 days
  • 2] 36 days
  • 3] 40 days
  • 4] 54 days
Solution
6
Discuss

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?

  • 1] 36
  • 2] 24
  • 3] 18
  • 4] Cannot be determined
Solution
7
Discuss

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
8
Discuss

The charges per hour of internet surfing is increased by 25% then find the percentage decrease in the time period of surfing user (a net savy) who can afford only 10% increase in expenditure:

  • 1] 22%
  • 2] 12%
  • 3] 15%
  • 4] 9.09%
Solution
9
Discuss

 

6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?

  • 1]

    7

  • 2]

    8

  • 3]

    6

  • 4]

    4

Solution
10
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
# Quiz