Quiz Discussion

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

Course Name: Quantitative Aptitude

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?

  • 1]

    81

  • 2]

    82

  • 3]

    83

  • 4]

    84

Solution
2
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
3
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
4
Discuss

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

  • 1] 60
  • 2] 45
  • 3] 40
  • 4] 30
Solution
5
Discuss

40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?

  • 1]

    \({ \text{7}}\frac{2}{3}{ \text{ days}}\)

  • 2]

    \({ \text{6}}\frac{1}{5}{ \text{ days}}\)

  • 3]

    \({ \text{8}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

Solution
6
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
7
Discuss

A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.

  • 1] After 10 minutes
  • 2] After 12 minutes
  • 3] After 20 minutes
  • 4] After 8 minutes
Solution
8
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
9
Discuss

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

  • 4]

    \({ \text{7}}\frac{3}{4}{ \text{ days}}\)

Solution
10
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution
# Quiz