A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?

Course Name: Quantitative Aptitude

  • 1] 5
  • 2] 6
  • 3] 9
  • 4] 13
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?

  • 1] Rs. 76
  • 2] Rs. 56
  • 3] Rs. 44
  • 4] Rs. 40
Solution
2
Discuss

A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?

 

  • 1]

    \(10\frac{1}{2}{ \text{days}}\)

  • 2]

    \(12\frac{2}{3}{ \text{days}}\)

  • 3]

    \(13\frac{1}{3}{ \text{days}}\)

  • 4]

    \(8\frac{1}{4}{ \text{days}}\)

Solution
3
Discuss

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
4
Discuss

P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution
5
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
6
Discuss

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
7
Discuss

A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?

  • 1] 91 days
  • 2] 100 days
  • 3] 175 days
  • 4] None of these
Solution
8
Discuss

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

  • 1]

    \(13\frac{1}{3}{ \text{days}}\)

  • 2]

    14 days

  • 3]

    15 days

  • 4]

    \(16\frac{2}{3}{ \text{days}}\)

Solution
9
Discuss

16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days. 12 men started the work and after 4 days 12 boys joined them. In how many days can they finish the remaining work ?

  • 1] 6
  • 2] 12
  • 3] 16
  • 4] None of these
Solution
10
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution