Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?
Solution |
2
Discuss
|
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?
Solution |
3
Discuss
|
Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?
Solution |
4
Discuss
|
There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?
Solution |
5
Discuss
|
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Solution |
6
Discuss
|
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Solution |
7
Discuss
|
25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?
Solution |
8
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
9
Discuss
|
A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?
Solution |
10
Discuss
|
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?
Solution |