X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
13 * 1/3 days
15 days
20 days
26 days
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Solution |
2
Discuss
|
A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?
Solution |
3
Discuss
|
4 men and 10 women were put on work. They completed \(\frac{1}{3}\) of the work in 4 days. After this 2 men and 2 women were increased. They completed \(\frac{2}{9}\) more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased?
Solution |
4
Discuss
|
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Solution |
5
Discuss
|
Three pipes A,B and C attached to a cistern. A can fill it in 10 min, B in 15 min, C is a waste pipe for emptying it. After opening both the pipes A and B, a man leaves the cistern and returns when the cistern should have been just full. Finding, however, that the waste pipe had left open, he closes it and the cistern now gets filled in 2 min. In how much time the pipe C, if opened alone, empty the full cistern?
Solution |
6
Discuss
|
A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?
Solution |
7
Discuss
|
If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:
Solution |
8
Discuss
|
A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days. How many days will B take to complete the task if he works alone?
Solution |
9
Discuss
|
8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work ?
Solution |
10
Discuss
|
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
Solution |