25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A pipe can fill a tank in 0.9 hours and another pipe can empty in 0.7 hours. If tank is completely filled and both pipes are opened simultaneously then 450 liters of water is removed from the tank is 2.5 hours. What is the capacity of the tank?
Solution |
2
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
3
Discuss
|
A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?
Solution |
4
Discuss
|
If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
Solution |
5
Discuss
|
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
Solution |
6
Discuss
|
A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?
Solution |
7
Discuss
|
If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?
Solution |
8
Discuss
|
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
Solution |
9
Discuss
|
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
Solution |
10
Discuss
|
Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?
Solution |