A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

Course Name: Quantitative Aptitude

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
2
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
3
Discuss

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60

Solution
4
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
5
Discuss

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
6
Discuss

A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job ?

  • 1] 27 days
  • 2] 36 days
  • 3] 40 days
  • 4] 54 days
Solution
7
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
8
Discuss

A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?

 

  • 1] 5 hours
  • 2] 4 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
9
Discuss

If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster then C, than the number of days C alone can complete the work is ?

  • 1] 44 days
  • 2] 33 days
  • 3] 22 days
  • 4] 11 days
Solution
10
Discuss

Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?

  • 1] 20 minutes
  • 2] 30 minutes
  • 3] 40 minutes
  • 4] 50 minutes
Solution
# Quiz