A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
30 days
40 days
60 days
70 days
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be
Solution |
10
Discuss
|
Two pipes A and B can fill a cistern in 12 min and 16 min respectively. Both the pipes are opened together for a certain time but due to some obstruction, the flow of water was restricted to 78 of full flow in pipe A and 56 of full in pipe B. This obstruction is removed after some time and the tank are now filled in 3 min from that moment. How long was it before the full flow?
Solution |
2
Discuss
|
40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?
Solution |
3
Discuss
|
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?
Solution |
4
Discuss
|
Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?
Solution |
5
Discuss
|
If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in:
Solution |
6
Discuss
|
A pipe can fill a tank in 0.9 hours and another pipe can empty in 0.7 hours. If tank is completely filled and both pipes are opened simultaneously then 450 liters of water is removed from the tank is 2.5 hours. What is the capacity of the tank?
Solution |
7
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in 1313 days. The money will be divided in the ratio?
Solution |
8
Discuss
|
Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
Solution |
9
Discuss
|
At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?
Solution |