To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?
Solution |
2
Discuss
|
Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?
Solution |
3
Discuss
|
A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?
Solution |
4
Discuss
|
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?
Solution |
5
Discuss
|
12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?
Solution |
6
Discuss
|
If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?
Solution |
7
Discuss
|
A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?
Solution |
8
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
9
Discuss
|
A can do a piece of work in 70 days and B is 40% more efficient then A. Then the number of days taken by B to do the same work is = ?
Solution |
10
Discuss
|
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ?
Solution |