A can do a work in 15 days and B in 20 days. If they together work on it for 4 days, what fraction of the work will be left ?
1/13
6/11
9/17
8/15
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?
Solution |
2
Discuss
|
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Solution |
3
Discuss
|
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
Solution |
4
Discuss
|
40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?
Solution |
5
Discuss
|
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Solution |
6
Discuss
|
12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?
Solution |
7
Discuss
|
6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?
Solution |
8
Discuss
|
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Solution |
9
Discuss
|
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
Solution |
10
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |