A can do a work in 15 days and B in 20 days. If they together work on it for 4 days, what fraction of the work will be left ?
1/13
6/11
9/17
8/15
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it?
Solution |
2
Discuss
|
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution |
3
Discuss
|
A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?
Solution |
4
Discuss
|
Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?
Solution |
5
Discuss
|
A 10 hectare field is reaped by 2 men, 3 women and 4 children together in 10 days. If working capabilities of a man, a woman and a child are in the ratio 5 : 4 : 2, then a 16 hectare field will be reaped by 6 men, 4 women and 7 children in = ?
Solution |
6
Discuss
|
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?
Solution |
7
Discuss
|
A and B can do a piece of work in 12 days, B and C in 8 days and C and A in 6 days. How long would B take to do the same work alone ?
Solution |
8
Discuss
|
Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?
Solution |
9
Discuss
|
A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?
Solution |
10
Discuss
|
A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?
Solution |