Quiz Discussion

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

Course Name: Quantitative Aptitude

  • 1]

    \(13\frac{1}{3}{ \text{days}}\)

  • 2]

    14 days

  • 3]

    15 days

  • 4]

    \(16\frac{2}{3}{ \text{days}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?

  • 1] 1 hour
  • 2] 2 hours
  • 3] 3 hours
  • 4] 4 hours
  • 5] 5 hours
Solution
2
Discuss

If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for days is = ?

  • 1]

    \(\frac{{{{ \text{p}}^{ \text{2}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 2]

    \(\frac{{{{ \text{p}}^{ \text{3}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 3]

    \(\frac{{{{ \text{n}}^{ \text{2}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

  • 4]

    \(\frac{{{{ \text{n}}^{ \text{3}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

Solution
3
Discuss

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
4
Discuss

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

  • 1]

    \({ \text{ 4}}\frac{4}{5}{ \text{ days}}\)

  • 2]

    \({ \text{ 3}}\frac{1}{3}{ \text{ days}}\)

  • 3]

    \({ \text{ 5}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{2}}\frac{2}{3}{ \text{ days}}\)

Solution
5
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
6
Discuss

If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?

  • 1] 6 days
  • 2] 7 days
  • 3] 8 days
  • 4] 10 days
Solution
7
Discuss

A and B can do a job in 7 days. A is \({ \text{1}}\frac{3}{4}\) times as efficient as B. The same job can be done by A alone in?

 

  • 1]

    \(9\frac{1}{3}{ \text{days}}\)

  • 2]

    11 days

  • 3]

    \(12\frac{1}{4}{ \text{days}}\)

  • 4]

    \(16\frac{1}{3}{ \text{days}}\)

Solution
8
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution
9
Discuss

A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?

 

  • 1]

    \({ \text{8}}\frac{1}{4}{ \text{days}}\)

  • 2]

    \(10\frac{1}{2}{ \text{days}}\)

  • 3]

    \(12\frac{2}{3}{ \text{days}}\)

  • 4]

    \(13\frac{1}{3}{ \text{days}}\)

Solution
10
Discuss

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  • 1]

    8 days

  • 2]

    10 days

  • 3]

    12 days

  • 4]

    15 days

Solution
# Quiz