A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Solution |
2
Discuss
|
Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?
Solution |
3
Discuss
|
6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?
Solution |
4
Discuss
|
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
Solution |
5
Discuss
|
12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?
Solution |
6
Discuss
|
A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?
Solution |
7
Discuss
|
There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?
Solution |
8
Discuss
|
A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?
Solution |
9
Discuss
|
While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?
Solution |
10
Discuss
|
If 10 persons can do a job in 20 days, then 20 person with twice the efficiency can do the same job in:
Solution |