Quiz Discussion

A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?

Course Name: Quantitative Aptitude

  • 1] Rs. 150
  • 2] Rs. 225
  • 3] Rs. 250
  • 4] Rs. 300
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?

  • 1] 35 days
  • 2] 50 days
  • 3] 45 days
  • 4] 40 days
Solution
2
Discuss

Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:

  • 1] 39 min.
  • 2] 46 min
  • 3] 40 min.
  • 4] 45 min.
Solution
3
Discuss

If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
4
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
5
Discuss

A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?

  • 1] 8 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
6
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
7
Discuss

 

6 women can complete a piece of work in 10 days, whereas 10 children alone take 15 days to complete the same piece of work. How many days will 6 women and 10 children together take to complete the piece of work?

  • 1]

    7

  • 2]

    8

  • 3]

    6

  • 4]

    4

Solution
8
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
9
Discuss

Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?

  • 1] 4 hours
  • 2] 5 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
10
Discuss

If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster then C, than the number of days C alone can complete the work is ?

  • 1] 44 days
  • 2] 33 days
  • 3] 22 days
  • 4] 11 days
Solution
# Quiz