A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before completion. The number of days for which C worked is

Course Name: Quantitative Aptitude

  • 1]

    4

  • 2]

    8

  • 3]

    12

  • 4]

    24

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
2
Discuss

If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in = ?

  • 1] 5 days
  • 2] 15 days
  • 3] 10 days
  • 4] 20 days
Solution
3
Discuss

If 2 men or 6 women or 4 boys can finish a work in 99 days, how many days will one man, one woman and one boy together take to finish the same work ?

  • 1] 44 days
  • 2] 54 days
  • 3] 64 days
  • 4] 104 days
  • 5] None of these
Solution
4
Discuss

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    18 days

Solution
5
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
6
Discuss

A, B and C completed a work costing Rs. 1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A ?

  • 1] Rs. 600
  • 2] Rs. 750
  • 3] Rs. 800
  • 4] Rs. 900
Solution
7
Discuss

P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?

 

  • 1] 10 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
8
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
9
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
10
Discuss

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?

  • 1] 100
  • 2] 60
  • 3] 75
  • 4] None of these
Solution
# Quiz