X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.

Course Name: Quantitative Aptitude

  • 1] 6 days
  • 2] 8.1 days
  • 3] 5.1 days
  • 4] 7 days
  • 5] None of these
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Three taps A, B and C together can fill an empty cistern in 10 minutes. The tap A alone can fill it in 30 minutes and the tap B alone in 40 minutes. How long will the tap C alone take to fill it?

  • 1] 16 minutes
  • 2] 24 minutes
  • 3] 32 minutes
  • 4] 40 minutes
Solution
2
Discuss

A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?

  • 1] 13.33 days
  • 2] 20 days
  • 3] 30 days
  • 4] 40 days
Solution
3
Discuss

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?

  • 1] 36
  • 2] 24
  • 3] 18
  • 4] Cannot be determined
Solution
4
Discuss

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ?

  • 1] 100 days
  • 2] 96 days
  • 3] 95 days
  • 4] 90 days
Solution
5
Discuss

If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?

  • 1] 5
  • 2] 6
  • 3] 10
  • 4] 12
Solution
6
Discuss

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?

  • 1] 6 days
  • 2] 8 days
  • 3] 15 days
  • 4] 16 days
Solution
7
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
8
Discuss

639 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?

  • 1] 210 days
  • 2] 213 days
  • 3] 214 days
  • 4] 215 days
Solution
9
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
10
Discuss

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
# Quiz