X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Anuj and Manoj can together paint their house in 30 days. After working for 20 days, Anuj has to go out and Manoj finished the remaining working the next 30 days. If Manoj had gone away after 20 days instead of Anuj, then Anuj would have completed the remaining work in ?
Solution |
2
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
3
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
4
Discuss
|
If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?
Solution |
5
Discuss
|
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
Solution |
6
Discuss
|
Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?
Solution |
7
Discuss
|
At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?
Solution |
8
Discuss
|
A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days. How many days will B take to complete the task if he works alone?
Solution |
9
Discuss
|
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Solution |
10
Discuss
|
If the expenditure of gas on burning 6 burners for 6 hours a day for 8 days is Rs. 450, then how many burners can be used for 10 days at 5 hours a day for Rs. 625 ?
Solution |