A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

Course Name: Quantitative Aptitude

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
2
Discuss

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
3
Discuss

A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
4
Discuss

A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?

 

  • 1] 5 hours
  • 2] 4 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
5
Discuss

A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?

  • 1] 18 days
  • 2] 24 days
  • 3] 9 days
  • 4] 12 days
Solution
6
Discuss

A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:

  • 1] 9 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
7
Discuss

A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

 

  • 1] 20
  • 2] 25
  • 3] 30
  • 4] 10
Solution
8
Discuss

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done \(\frac{3}{5}\) part of the work, the number of men he can withdraw so that his work may still be finished in time is?

 

  • 1] 45
  • 2] 40
  • 3] 35
  • 4] 30
Solution
9
Discuss

P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

  • 1] 18 days
  • 2] 24 days
  • 3] 30 days
  • 4] 12 days
Solution
10
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
# Quiz