A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

Course Name: Quantitative Aptitude

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can do a job in 2 days; B and C can do it in 4 days; A and C in \({ \text{2}}\frac{2}{5}\) days. The number of days required for A to do the job alone is = ?

 

  • 1] 1
  • 2] 3
  • 3] 6
  • 4] 12
Solution
2
Discuss

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
3
Discuss

A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?

  • 1] 4 days
  • 2] 6 days
  • 3] 9 days
  • 4] 18 days
Solution
4
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
5
Discuss

Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?

  • 1] 4 hours
  • 2] 5 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
6
Discuss

Two pipes, P and Q can fill a cistern in 12 and 15 minutes respectively. Both are opened together, but at the end of 3 minutes, P is turned off. In how many more minutes will Q fill the cistern?

  • 1]

    7 minutes

  • 2]

    \(7\frac{1}{2}\) minutes

  • 3]

    8 minutes

  • 4]

    \(8\frac{1}{4}\) minutes

Solution
7
Discuss

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

  • 1]

    11 days

  • 2]

    13 days

  • 3]

    20 3/17 days

  • 4]

    None of these

Solution
8
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
9
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
10
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
# Quiz