A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?
Solution |
2
Discuss
|
A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?
Solution |
3
Discuss
|
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
Solution |
4
Discuss
|
4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?
Solution |
5
Discuss
|
Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.
Solution |
6
Discuss
|
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?
Solution |
7
Discuss
|
A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?
Solution |
8
Discuss
|
P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?
Solution |
9
Discuss
|
20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?
Solution |
10
Discuss
|
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before completion. The number of days for which C worked is
Solution |