To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

Course Name: Quantitative Aptitude

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?

 

  • 1] 5 hours
  • 2] 8 houras
  • 3] 4 hours
  • 4] 6 hours
Solution
2
Discuss

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be

  • 1]

    5 days

  • 2]

    4 days

  • 3]

    6 days

  • 4]

    7 days

Solution
3
Discuss

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
4
Discuss

A is thrice as good a workman as B and so takes 60 days less than B for doing a job. The time in which they can do the job together is = ?

  • 1]

    \(22\frac{1}{2}{ \text{days}}\)

  • 2]

    30 days

  • 3]

    45 days

  • 4]

    60 days

Solution
5
Discuss

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
6
Discuss

A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

 

  • 1] 20
  • 2] 25
  • 3] 30
  • 4] 10
Solution
7
Discuss

Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?

  • 1] 4 hours
  • 2] 5 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
8
Discuss

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
9
Discuss

A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?

  • 1] 30 days
  • 2] 40 days
  • 3] 50 days
  • 4] 70 days
Solution
10
Discuss

18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?

  • 1] 54 days
  • 2] 63 days
  • 3] 76 days
  • 4] 81 days
  • 5] None of these
Solution