To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?
Solution |
2
Discuss
|
If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days then the time taken by 15 men and 20 boys to do the same type of work will be
Solution |
3
Discuss
|
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Solution |
4
Discuss
|
A is thrice as good a workman as B and so takes 60 days less than B for doing a job. The time in which they can do the job together is = ?
Solution |
5
Discuss
|
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?
Solution |
6
Discuss
|
A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?
Solution |
7
Discuss
|
Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?
Solution |
8
Discuss
|
A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?
Solution |
9
Discuss
|
A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?
Solution |
10
Discuss
|
18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?
Solution |