45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?
6 days
8 days
\({ \text{6}}\frac{2}{3}{ \text{ days}}\)
\({ \text{7}}\frac{3}{4}{ \text{ days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?
Solution |
2
Discuss
|
If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?
Solution |
3
Discuss
|
A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?
Solution |
4
Discuss
|
Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.
Solution |
5
Discuss
|
If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?
Solution |
6
Discuss
|
A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were
Solution |
7
Discuss
|
60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?
Solution |
8
Discuss
|
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:
Solution |
9
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |
10
Discuss
|
A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?
Solution |
# | Quiz |
Copyright © 2020 Inovatik - All rights reserved