Quiz Discussion

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

Course Name: Quantitative Aptitude

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

  • 4]

    \({ \text{7}}\frac{3}{4}{ \text{ days}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
2
Discuss

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

  • 1] 5 days
  • 2] 6 days
  • 3] 9 days
  • 4] 10 days
Solution
3
Discuss

A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:

  • 1] 10 days
  • 2] 12 days
  • 3] 15 days
  • 4] 16 days
Solution
4
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
5
Discuss

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

  • 1] 3 days
  • 2] 4 days
  • 3] 4.5 days
  • 4] 5.4 days
Solution
6
Discuss

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?

  • 1] 4
  • 2] 5
  • 3] 7
  • 4] 8
Solution
7
Discuss

Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

  • 1] 6:20 PM
  • 2] 6:30 PM
  • 3] 6:36 PM
  • 4] 6:42 PM
Solution
8
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution
9
Discuss

A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
10
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
# Quiz