If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for days is = ?

Course Name: Quantitative Aptitude

  • 1]

    \(\frac{{{{ \text{p}}^{ \text{2}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 2]

    \(\frac{{{{ \text{p}}^{ \text{3}}}}}{{{{ \text{n}}^{ \text{2}}}}}\)

  • 3]

    \(\frac{{{{ \text{n}}^{ \text{2}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

  • 4]

    \(\frac{{{{ \text{n}}^{ \text{3}}}}}{{{{ \text{p}}^{ \text{2}}}}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
2
Discuss

A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?

  • 1]

    \({ \text{3}}\frac{5}{{12}}\)

  • 2]

    \({ \text{3}}\frac{9}{{13}}\)

  • 3]

    \({ \text{7}}\frac{5}{{12}}\)

  • 4]

    \({ \text{7}}\frac{5}{{13}}\)

Solution
3
Discuss

A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:

  • 1] 9 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
4
Discuss

If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster then C, than the number of days C alone can complete the work is ?

  • 1] 44 days
  • 2] 33 days
  • 3] 22 days
  • 4] 11 days
Solution
5
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
6
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
7
Discuss

A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days. How many days will B take to complete the task if he works alone?

  • 1]

    9 days

  • 2]

    7 days

  • 3]

    5 days

  • 4]

    3 days

  • 5]

    None of these

Solution
8
Discuss

A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?

  • 1] 3 days
  • 2] 5 days
  • 3] 4 days
  • 4] 2 days
Solution
9
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
10
Discuss

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?

  • 1] 36
  • 2] 24
  • 3] 18
  • 4] Cannot be determined
Solution