3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

Course Name: Quantitative Aptitude

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.

  • 1] 3150
  • 2] 3450
  • 3] 3500
  • 4] 3600
  • 5] None of these
Solution
2
Discuss

A tank can be filled with water by two pipes A and B together in 36 minutes. If the pipe B was stopped after 30 minutes, the tank is filled in 40 minutes. The pipe B can alone fill the tank in:

  • 1] 45 minutes
  • 2] 60 minutes
  • 3] 75 minutes
  • 4] 90 minutes
Solution
3
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
4
Discuss

Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:

  • 1]

    \(\frac{2}{3}\) hours

  • 2]

    \(\frac{3}{4}\) hours

  • 3]

    \(\frac{3}{2}\) hours

  • 4]

    \(\frac{4}{3}\) hours

Solution
5
Discuss

Two pipes A and B can fill a cistern in 12 min and 16 min respectively. Both the pipes are opened together for a certain time but due to some obstruction, the flow of water was restricted to \(\frac{7}{8}\) of full flow in pipe A and \(\frac{5}{6}\) of full in pipe B. This obstruction is removed after some time and the tank are now filled in 3 min from that moment. How long was it before the full flow?

 

  • 1] 8 min
  • 2] 3 min
  • 3] 5.6 min
  • 4] 4.5 min
  • 5] None of these
Solution
6
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
7
Discuss

If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:

  • 1] 48 days
  • 2] 36 days
  • 3] 45 days
  • 4] 50 days
Solution
8
Discuss

P is thrice as good a workman as Q and together they finish a piece of work in 24 days. The number of days taken by P alone to finish the work is:

  • 1]

    25 days

  • 2]

    22 days

  • 3]

    32 days

  • 4]

    34 days

Solution
9
Discuss

If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it?

  • 1] 10 days
  • 2] 11 days
  • 3] 9 days
  • 4] 12 days
Solution
10
Discuss

A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?

  • 1] 8 days
  • 2] 9 days
  • 3] 10 days
  • 4] 11 days
Solution