Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?

Course Name: Quantitative Aptitude

  • 1] 1 hour
  • 2] 2 hours
  • 3] 3 hours
  • 4] 4 hours
  • 5] 5 hours
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
2
Discuss

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

  • 1] 75
  • 2] 100
  • 3] 125
  • 4] 50
Solution
3
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
4
Discuss

A is twice as good a workman as B. If they work together, they can complete a job in 18 days. If A alone does the job, in how many days he will complete the job ?

  • 1] 27 days
  • 2] 36 days
  • 3] 40 days
  • 4] 54 days
Solution
5
Discuss

Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?

  • 1] 6:20 PM
  • 2] 6:30 PM
  • 3] 6:36 PM
  • 4] 6:42 PM
Solution
6
Discuss

Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:

  • 1] 39 min.
  • 2] 46 min
  • 3] 40 min.
  • 4] 45 min.
Solution
7
Discuss

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?

  • 1] 100
  • 2] 60
  • 3] 75
  • 4] None of these
Solution
8
Discuss

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work ?

  • 1] 10 days
  • 2] 12 days
  • 3] 14 days
  • 4] 16 days
  • 5] None of these
Solution
9
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
10
Discuss

A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution